Small second dwellings are becoming an increasingly popular option for Victorian homeowners looking to accommodate family members, create additional living space or generate rental income.
Recent changes to Victoria’s planning provisions have made these developments more flexible, but there are still important building and planning requirements that need to be considered.
For builders and designers, understanding where the exemptions apply, and where further approvals are required, is essential to avoiding complications later in the project.
WHAT CHANGED IN OCTOBER 2026?
On 15 October 2026, Amendment VC306 introduced several changes to Victoria’s small second dwelling planning provisions.
The most significant change was an increase in the maximum floor area from 60m² to 80m².
The amendment also clarified how floor area is calculated and removed the planning requirement to provide an access pathway, helping to simplify aspects of the planning approval process.
Under the updated planning definition, a small second dwelling must be located on the same lot as an existing dwelling and provide self-contained accommodation, including cooking and bathroom facilities.
The changes to the planning system are intended to be reflected in the Building Regulations 2018 and Minister’s Guideline 12 through separate amendments.
While the October 2026 planning changes increased the maximum floor area for small second dwellings to 80m², the Building Regulations initially retained the previous 60m² definition. This created a temporary inconsistency between the planning and building approval frameworks, highlighting the importance of checking which requirements apply when preparing a design.
DO SMALL SECOND DWELLINGS REQUIRE A PLANNING PERMIT?
In many Victorian residential and rural zones, small second dwellings can be constructed without a planning permit. However, this exemption does not apply to every property.
A planning permit may still be required where:
- The lot is less than 300m² in a residential zone.
- The land is within certain rural or green wedge zones.
- Specific planning overlays apply.
- Other provisions of the relevant planning scheme trigger a permit requirement.
For example, flood-related, environmental and heritage controls can introduce additional considerations. The absence of a planning permit requirement should never be assumed without checking the relevant planning scheme.
IS A BUILDING PERMIT STILL REQUIRED?
A building permit is still required for a small second dwelling, even where the project is exempt from obtaining a planning permit.
Planning permit exemptions simplify aspects of the approval process, but they don’t remove the obligation to demonstrate compliance with applicable building legislation.
The building permit assessment will consider relevant requirements under the Building Regulations 2018 and National Construction Code (NCC), including structural safety, fire safety, health and amenity, and energy efficiency.
Given the October 2026 changes, particular care should be taken with proposals between 60m² and 80m² while the corresponding building framework is being updated.
WHAT SITING REQUIREMENTS NEED TO BE CONSIDERED?
Small second dwellings must still satisfy applicable siting and amenity requirements.
Depending on the property and approval pathway, these may include:
Site coverage and garden area
The additional dwelling must be considered alongside the existing development when assessing the amount of the allotment occupied by buildings and the applicable garden area requirements.
Setbacks and building height
The proposed dwelling’s position in relation to boundaries, neighbouring properties and the existing dwelling can affect compliance.
Private open space
Applicable requirements for private open space must be considered for the proposed small second dwelling and the existing home.
Access and accessibility
Although the October amendment removed a planning access pathway requirement, designers must still check applicable building and accessibility requirements.
Neighbouring amenity
Depending on the design, matters such as overlooking, overshadowing and daylight access may also require assessment.
Identifying these considerations during the design stage can reduce the likelihood of substantial revisions later.
CAN A SMALL SECOND DWELLING BE RENTED OUT OR SUBDIVIDED?
A small second dwelling can be occupied by family members or rented to other occupants, subject to applicable residential tenancy requirements. However, the planning provisions do not allow a separate lot to be created for the small second dwelling.
This distinction is important for clients considering a second dwelling as a potential future investment or subdivision opportunity.
WHY EARLY COMPLIANCE CHECKS MATTER
The increase to 80m² provides greater flexibility, but it doesn’t eliminate the need for careful assessment.
Before progressing a design, builders and designers should confirm the relevant planning controls, applicable building requirements and any site-specific restrictions.
This is particularly important during periods of regulatory change, when different parts of the approval framework may not yet be fully aligned.
At Deemed to Perform, we assist builders, designers and property owners with practical building compliance advice, helping identify regulatory requirements and potential complications before they affect project progress.
Planning a small second dwelling? Contact Deemed to Perform for guidance on the building compliance considerations relevant to your project.