When a building project runs into a regulatory issue, the next step isn’t always straightforward.
A design might not be able to satisfy a particular building regulation, or a building permit has been refused. In some circumstances, the Building Appeals Board (BAB) may provide a pathway for resolving the matter.
However, a modification application and an appeal are two different processes, and understanding which one applies is an important starting point.
Here’s what Victorian builders, designers and property owners should know.
WHAT IS THE BUILDING APPEALS BOARD?
The Building Appeals Board is an independent statutory body established under the Building Act 1993 (Vic).
It makes determinations on certain building-related matters, including regulatory modifications, appeals against specific decisions, disputes and compliance assessments.
The BAB has defined powers under legislation, meaning not every disagreement or compliance issue can automatically be referred to it.
The type of application depends on the circumstances and the outcome being sought.
WHAT IS A BAB MODIFICATION APPLICATION?
A modification application generally involves seeking a determination that a particular building regulation or provision of the Building Code of Australia should not apply, or should apply in a modified or varied form.
Under section 160 of the Building Act 1993, the BAB may consider whether:
- Applying a particular provision is inappropriate in the circumstances; or
- Modifying or varying a provision would be reasonable and not detrimental to the public interest.
For example, a project involving an existing building may present physical constraints that make compliance with a particular requirement difficult. Rather than simply proceeding with a non-compliant design, the owner might need to consider whether a modification application is appropriate. However, difficulty meeting a regulation does not automatically justify a modification. The application must be supported by a clear explanation and relevant evidence.
Different provisions apply to modifications involving access requirements under section 160B.
WHAT IS A BAB APPEAL?
An appeal is different because it involves challenging a decision made under the Building Act or Building Regulations.
Depending on the circumstances, appealable decisions may include:
- Refusal to issue or amend a building permit.
- Certain council report and consent decisions.
- Decisions relating to building notices or building orders.
- Certain protection work determinations.
- Other decisions specifically identified under the legislation.
For example, if a building permit application has been refused, an eligible party may have grounds to appeal that decision. The key difference is that a modification seeks an alternative application of a regulatory provision, while an appeal challenges an existing decision. Not every decision can be appealed, and strict time limits may apply.
WHAT INFORMATION IS NEEDED FOR AN APPLICATION?
Whether preparing a modification or an appeal, the quality of the supporting documentation matters.
Depending on the application, relevant information may include:
Clear drawings and plans
Documentation should identify the building, relevant design elements and the specific matter being considered.
Relevant regulatory references
The application should identify the applicable legislation or regulatory provisions and clearly explain the issue.
Supporting evidence
Technical reports, photographs, specifications and other documents may be required to explain the circumstances.
A clear justification
For modification applications, it is particularly important to explain why the requested outcome is appropriate and how any potential adverse consequences will be addressed.
For appeals, the grounds for challenging the decision and the outcome being sought must be clearly presented.
The required documentation will depend on the type of proceeding and the circumstances of the project.
CAN A BAB APPLICATION DELAY YOUR PROJECT?
Preparing the application, gathering supporting evidence and progressing through the BAB process can take time.
Appeals also have prescribed lodgement periods, which means it’s important to seek advice promptly when a decision is received.
A BAB application should not be treated as an automatic approval pathway or a guaranteed way to resolve a compliance issue.
Where possible, identifying regulatory constraints early and considering available options before progressing too far with a design can help avoid unnecessary delays and costs.
WHY UNDERSTANDING THE DIFFERENCE MATTERS
Confusing modifications with appeals can lead to the wrong application being prepared, additional costs or delays in resolving the original issue.
Before proceeding, it’s important to establish:
- What regulation or decision is causing the issue?
- Is the objective to seek a modification or challenge a decision?
- Does the BAB have jurisdiction to consider the matter?
- What evidence is required to support the application?
Getting these details right from the beginning can make the process clearer for everyone involved.
STAY INFORMED WITH DTP INSIDER
Building regulations and approval pathways can be complex, particularly when a project involves unusual circumstances or regulatory challenges.
At Deemed to Perform, we believe practical industry knowledge makes a difference when navigating these situations.
Throughout November, DTP Insider is focusing on Building Appeals Board modifications and appeals, with practice notes designed to help building practitioners better understand these processes and the considerations involved.
Want to build your understanding of BAB applications?
Explore DTP Insider for practical resources, technical insights and industry guidance.